Articles
Industry News
The Future Homes Standard: A guide to compliant masonry construction
Posted by Lignacite
According to Government data released in 2022, residential dwellings account for 20% of UK greenhouse gas emissions. It’s little surprise, therefore, that the construction industry has a major role to play in helping the UK meet its net-zero target by 2050.
The Future Homes Standard gives the construction industry greater clarity on what will be expected of new homes in terms of carbon emissions, energy efficiency and fabric performance. As a result, the changes will influence decisions made by architects, specifiers, developers and contractors across England, as well as materials manufacturers like Lignacite.
In this guide, we explore some of the key facets of the Future Homes Standard and consider what the changes mean for masonry construction.
Future Homes Standard at a glance
What is the Future Homes Standard?
The latest iteration of Building Regulations Part L, setting tougher energy and carbon requirements for new homes in England.
When does it come into force?
24 March 2027.
What is the headline carbon-reduction target?
It is expected to achieve at least 75% lower carbon emissions than homes built to 2013 standards.
What does it apply to?
New homes in England.
What is the Future Homes Standard?
The Future Homes Standard (FHS) sets new energy efficiency requirements for domestic buildings in England. The aim is to significantly reduce carbon emissions and make homes zero-carbon ready. It forms part of the government’s wider ambition to achieve net zero greenhouse gas emissions by 2050.
The Future Homes Standard is being delivered through changes to Building Regulations and a revised Approved Document L, alongside related changes to the way building performance is assessed.
In the simplest terms, the Government expects homes built to the new standard to produce at least 75% fewer operational carbon emissions than homes built to the 2013 requirements. The 2021 changes to Part L were a step towards this, delivering around a 30% reduction when compared with the 2013 standard. Future Homes Standard takes this further.
Meeting the new standard will require a combination of measures, including low-carbon heating, improved building fabric standards and on-site renewable electricity generation.
FHS compliance methods will also be assessed differently. The Government plans to introduce the Home Energy Model (HEM) with a view to replacing SAP, although SAP 10.3 is the approved methodology at the time of writing.
The Future Homes Standard specifically applies to new homes in England. A Future Buildings Standard introduces similar requirements for new non-domestic buildings. As such, both are relevant for construction professionals working across both residential and commercial projects.
Is the Future Homes Standard in force?
At the time of writing, in autumn 2026, the Future Homes Standard has been published but it is not yet enforced. For most home building work, the new requirements will be implemented on 24 March 2027.
Transitional arrangements mean that some projects can continue under the previous standard. For most buildings, this will apply when a building control notice or application has been submitted before 24 March 2027 and work starts on site before 24 March 2028. There are separate arrangements for higher-risk buildings.
Is the Future Homes Standard mandatory?
Yes. The Future Homes Standard forms part of new legislation that amends the Building Regulations in England. Compliance will be a legal requirement for new homes that fall within the new regulations, unlike voluntary sustainability assessment schemes such as BREEAM.
This means architects, specifiers, developers and contractors involved in delivering new homes in England will need to ensure that their designs and construction meet the standard.
However, not every project will move onto the new standard at the same time. Transitional arrangements allow some developments to continue under previous requirements, as we will see later in this article.
What is the implementation timeline?
The key dates for the Future Homes Standard are:
- 24 March 2026: The Future Homes and Buildings Standards were published, together with the regulations and updated guidance needed to implement them.
- 24 March 2027: For most building work, the new requirements come into force.
- 24 September 2027: Requirements for higher-risk building work are introduced, which is subject to separate transitional arrangements.
- 24 March 2028: For most non-higher-risk projects seeking to use the transitional arrangements, building work must have commenced by this date.
These dates are correct at the time of publication. Timelines may change. Check the latest government guidance when planning projects.
How does the Future Homes Standard differ from Part L?
The Future Homes Standard and Part L are not separate schemes. The Government describes the Standard as the latest version of Part L of the Building Regulations.
One of the main changes is the requirement for on-site renewable electricity generation. As a result, many new residential buildings will be built with solar panels.
Changes to heating systems will also support carbon reduction. The Standard does not introduce a ban on gas boilers, but government guidance states that gas boilers will not meet the required performance standard. Low-carbon heating systems such as heat pumps are therefore expected to become the norm in new homes.
Fabric performance remains an important factor in compliance. Notional building specification targets will be higher than under the 2021 standard, which may lead designers to increase insulation or adjust wall and floor build-ups. However, compliance is assessed across the whole dwelling rather than individual elements, so there is flexibility in how targets are achieved.
Airtightness and ventilation also need to be considered together. Reducing air leakage can limit heat loss, but ventilation remains essential for indoor air quality. The 2026 standards therefore include updated guidance under both Approved Document L and Approved Document F.
The way compliance is calculated is changing too. At the time of writing, SAP 10.3 remains the only approved methodology for demonstrating compliance with the Future Homes Standard. However, the Government intends to introduce the new Home Energy Model (HEM) alongside SAP before HEM eventually replaces it.
What are the transitional arrangements?
The Future Homes Standard includes transitional arrangements so that some projects already progressing through building control do not have to switch immediately to the new requirements.
For most non-higher-risk buildings, the previous requirements may continue to apply where a building notice, initial notice or application for building control approval with full plans is submitted before 24 March 2027, provided that work on the building commences before 24 March 2028.
It’s important to highlight that transitional provisions apply to individual dwellings rather than entire developments. This means some plots within the same development could be subject to 2021 requirements while others have to comply with the Future Homes Standard.
Higher-risk buildings, including those over 18 metres or seven storeys tall, will follow a different timetable. The relevant requirements come into force for higher-risk buildings on 24 September 2027. Separate transitional arrangements will apply to projects that already have a valid building control approval application in place.
What does the FHS mean for masonry construction?
The Future Homes Standard does not require a fundamental change in the use of masonry construction. Concrete blockwork can continue to form part of compliant wall systems, although overall construction may need to change to meet new performance targets.
This is because compliance depends on the performance of the whole building rather than the block alone. Depending on the specification, designers may therefore need to increase insulation levels, alter cavity widths for external walls or make other changes to the wall build-up.
Construction quality will also become more important. Heat can escape through junctions where walls meet floors, roofs and other walls, as well as around windows and doors. Careful detailing and workmanship can help minimise thermal bridging and maintain the intended airtightness and thermal performance of the building.
Psi values provide a practical way of assessing this. By calculating the expected amount of heat lost through a junction, specifiers and energy assessors can estimate the overall heat loss from a dwelling. Accurate junction details and Psi values therefore help demonstrate that thermal bridging has been accounted for within the compliance assessment.
Masonry also offers benefits that are not captured by U-values alone. Concrete blocks have thermal mass, meaning they can absorb heat and release it again as temperatures change. When considered alongside factors such as shading and ventilation, this can help moderate internal temperatures and reduce the risk of summertime overheating.
How can concrete blocks contribute to compliant wall specifications?
Block choice can influence how easily a wall achieves its target U-value. Different blocks have different thermal conductivity values, which affects the amount and type of insulation required elsewhere in the wall. Specifiers therefore need to consider fabric quality, block thermal conductivity and insulation performance together when developing a compliant construction.
However, thermal performance is only one part of the specification. The same wall may also need to satisfy Building Regulations technical requirements for structural performance, fire safety and resistance to sound.
This means the most appropriate block is not necessarily the one with the lowest thermal conductivity. Strength, density, acoustic performance, fire performance and the intended application all need to be considered alongside energy efficiency when selecting a wall system.
Which Lignacite blocks are suitable for energy-efficient homes?
A number of Lignacite blocks can form part of energy-efficient wall specifications, with the most appropriate choice depending on the application and overall wall build-up.
For projects looking to reduce embodied carbon alongside meeting required thermal performance, the Lignacite ECO Range is a strong option. ECO 50 and ECO 70 contain 50% and 70% recycled content respectively and are supported by independently verified Environmental Product Declarations (EPDs).
To identify a suitable product, specifiers can use our Product Selector Tool to narrow the range by application and performance requirements. The Product Specification Builder can then be used to create product specification documentation for the selected block.